验收专家组意见
|
一条宽度20米,一条宽度8米,道路两侧种植油松,株距3米,树种高度1.2~1.5米;两条主干道两侧设置80*80米的方格网,方格网围堰规格,底宽1.5米*高度0.8米*顶宽0.8米,方格网内围堰周边种植油松,株距3米,树种高度0.8米~1.2米,方格网内播撒草苜蓿和沙打旺;方格网之间留有6米宽的通道。经不完全统计,该矿栽植灌木93余株,平整土方量127万立方米,治理费用共计573.4万元。
该矿2013年1月至2015年12月地质环境治理已按照要求完成,面积共计2.1227km2,范围坐标(北京54坐标)如下:
1,4381912.479,37466176.72 2,4381792.785,37466036.55
3,4381445.166,37466358.93 4,4381427.954,37466315.43
5,4381561.654,37466140.86 6,4381249.688,37465917.88
7,4380996.295,37466195.66 8,4380600.239,37466200.98
9,4380587.506,37466121.98 10,4380488.186,37466113.06
11,4380418.153,37466277.43 12,4380368.493,37466273.61
13,4380358.306,37466316.93 14,4380425.793,37466388.29
15,4380586.233,37466450.73 16,4380614.246,37466574.32
17,4380614.246,37466708.12 18,4380563.313,37466709.39
19,4380537.846,37466790.94 20,4380418.153,37466788.39
21,4380376.133,37466747.62 22,4380287,37466736.15
23,4380266.626,37466650.78 24,4380308.646,37466336.05
25,4380070.533,37466183.14 26,4380078.617,37466097.48
27,4380018.215,37465886.24 28,4380010.333,37465709.38
29,4379918.052,37465550.31 30,4379784.337,37465612.26
31,4379658.418,37465600.54 32,4379332.63,37466016.09
33,4379365.736,37466123.13 34,4379215.483,37466269.66
35,4379228.217,37466333.37 36,4379721.791,37466777.88
|
|
37,4379812.686,37467124.57 38,4379879.581,37466881.54
39,4379952.851,37466841.1 40,4380011.148,37466935.22
41,4380194.508,37466972.17 42,4381177.244,37467029.63
43,4381598.717,37467023.26 44,4381804.292,37466857.48
45,4381876.872,37466773.38 46,4381995.292,37466707.12
47,4382108.618,37466589.9 48,4382085.698,37466505.8
49,4382043.678,37466487.96 50,4381940.539,37466628.12
51,4381712.612,37466619.2 52,4381552.172,37466582.25
53,4381516.519,37466526.19 54,4381578.912,37466451.01
55,4381631.119,37466457.38
经验收组核查验收资料、踏勘矿山现场,准格尔旗云凯煤炭有限责任公司煤矿首期(2013年1月至2015年12月)矿山地质环境治理工程达到要求,矿山地质环境治理工程通过验收。
|